Exemplo de Valor Agregado: IDC, IDP e o Business Case

Este é um exemplo de valor agregado completo, de um projeto de oito meses: os números do plano e da execução, os índices calculados à mão e o que o desvio muda na decisão de investir. Aula 7 de 8 do curso gratuito de Avaliação de Projetos.

Este é um exemplo de valor agregado completo, de um projeto de oito meses: os números do plano e da execução, os índices calculados à mão e o que o desvio muda na decisão de investir. Aula 7 de 8 do curso gratuito de Avaliação de Projetos.

Em contexto

  • Tema: Proyectos, PMO y Riesgos — Gestión de proyectos, oficinas de proyecto y riesgo del portafolio.
  • Fonte: Escritório de Projetos
  • Publicado: 02/11/2026

Continuar lendo na fonte original →

Trecho publicado automaticamente pelo radar do site. O texto completo pertence ao veículo e está vinculado acima.

Why it matters

Projects rarely fail on the day they are declared failed. They fail months earlier, in a meeting where somebody saw the problem coming and calculated it was not in their interest to say so. Everything else — the slipping schedule, the stretching budget — is the visible consequence of that silence.

I read these things looking for where the risk sat before it became an incident. It was almost always already written in some register nobody reviewed, with an assigned owner who never found out they were one. A risk identified and not managed is worse than one never identified: it creates the false sense that there is control.

What usually goes wrong

The classic mistake is treating risk management as a deliverable of the planning phase. The matrix gets built, approved, filed. Nobody opens it again until closure, when it serves to document that the risk was foreseen — which is exactly the opposite of managing it.

What to watch

  • Who the sponsor is and how often they actually show up — not on the org chart, in the calendar.
  • Whether the status report shows any red projects: an all-green portfolio is a portfolio without information.
  • Which risks are identified, who owns each one, and when they were last reviewed.

How I read this entry

The way I would bring this down to earth is by shrinking the size of the deliveries. An eighteen-month project with nothing visible before month twelve is a bet, not a plan. I would rather have six deliveries that stand on their own, even if the total takes a little longer, because each one corrects the course.

The original story is published in another language; the excerpt is quoted as the publisher delivers it and the commentary is written in English.
Share

Comments

No comments yet. Yours can be the first.

Plain text only, no links. No email is requested. Comments are reviewed before they are published.

Living through this in your own team?

Open the chat and tell me how you're handling it. I'm interested in comparing notes.

Keep reading

More entries from the radar

See all
Darinel Ortega Online · I reply during the day
Today
Hello. I'm not selling anything here: this is for exchanging knowledge about technology.
Write whatever you like — you can send text, images or documents. Messages reach my console and I reply from there.
You are writing outside working hours. I will read you as soon as the day starts.

An open conversation to share knowledge. Messages reach my console and I reply from there.

Let us book a conversation

Pick the day and time that work for you. Thirty minutes, no sales pitch.

Video call

For a video call, just ask for one here and I'll send you the session link.